Panel schedule template and circuit directory
Enter each breaker by space number with what it feeds, its rating, poles and load, and Busbar lays out the panel schedule, adds up the load on each phase and prints a circuit directory cut to the size of your panel door. It flags a breaker loaded past its rating with continuous loads at 125 % (NEC 210.20(A)) and a main breaker larger than the bus rating (408.36). One panel at a time is free with no sign-up, print and PDF included; Pro is US$9 a month to save every panel of a job, print their directories together and download the schedule as a report with your company and job address. It adds up connected load, not an Article 220 load calculation, and only knows the circuits you enter, so trace each one on site.
- Printable directory
- Phase totals
- No sign-up
The breaker that protects this panel
From the label inside the panel
Where the power comes from and where that is. 408.4(B) requires it on feeder-supplied panels, except in one- and two-family dwellings.
3–7.5 in: measure the card holder on the door
4–9 in
Printed at the bottom of the directory. 408.4(A) asks for abbreviations and symbols to be explained.
Circuits
Odd spaces on the left, even on the right, as in most panels. Describe each circuit by what it feeds and where, not by who uses the room, and mark unused breakers as spares. Continuous means the load runs 3 hours or more.
Range 3/5, 2-pole breaker
Water heater, basement 7/9, 2-pole breaker
EV charger, garage 10/12, 2-pole breaker
Phase A carries the most: 144.3 A
That is below the 200 A rating of the main breaker and bus, and no breaker is loaded past its rating. This screens the loads you entered; it is not a load calculation.
NEC 2023 · 210.20(A) · 408.36 · 120/240 V single-phase
Panel
- Panel
- Main panel
- Supply system
- 120/240 V single-phase
- Main or upstream breaker
- 200 A
- Bus rating
- 200 A
- Spaces
- 24
Circuits
- 1 · A · Kitchen counter receptacles, left of sink · 20 A 1P
- 1,500 VA · 12.5 A
- 2 · A · Kitchen island receptacles · 20 A 1P
- 1,500 VA · 12.5 A
- 3/5 · B/A · Range · 40 A 2P
- 8,000 VA · 33.3 A
- 4 · B · Dishwasher · 20 A 1P
- 1,200 VA · 10.0 A
- 6 · A · Laundry receptacle · 20 A 1P
- 1,500 VA · 12.5 A
- 7/9 · B/A · Water heater, basement · 30 A 2P, continuous
- 4,500 VA · 18.8 A
- 8 · B · Bedrooms 2 and 3, lights and receptacles · 15 A 1P
- 1,000 VA · 8.3 A
- 10/12 · A/B · EV charger, garage · 50 A 2P, continuous
- 9,600 VA · 40.0 A
- 11 · B · Spare · 20 A 1P
- —
Connected load by phase
- Phase A: 15,550 VA
- 129.6 A
- Phase A with continuous loads × 125 %
- 144.3 A
- Phase B: 13,250 VA
- 110.4 A
- Phase B with continuous loads × 125 %
- 125.1 A
- Largest deviation from the phase average (VA)
- 8.0 %
Checks
- Every breaker is at least its load, continuous loads × 125 %
- 210.20(A)
- Yes
- Main or upstream breaker (200 A) not above the bus rating (200 A)
- 408.36
- Yes
- Heaviest phase, connected load (144.3 A) vs. the 200 A rating
- Below
- Spaces are numbered odd on the left and even on the right. Each row of two spaces is on one phase, A, B (and C) repeating down the panel, and a 2- or 3-pole breaker takes the spaces below it on the same side. Check the wiring diagram on the panel label.
- Current is VA ÷ line-to-neutral voltage for 1 pole, VA ÷ line-to-line voltage for 2 poles and VA ÷ (1.732 × line-to-line voltage) for a balanced 3-pole load. VA is split equally between a breaker’s poles and phase currents are added arithmetically, which overstates line-to-line loads on a three-phase panel.
- Continuous loads (3 hours or more) count at 125 % against their breaker, per 210.20(A). The exception for assemblies listed for 100 % operation is not applied.
- 408.30 (408.14 in NEC 2026) requires the panelboard rating to be at least the load calculated under Article 220 (Article 120 in NEC 2026), which applies demand factors. Connected load is usually higher, so a phase above the rating here is a reason to run that calculation.
- Not checked: the 408.36 exceptions, motors, demand factors, multiwire branch circuits, tandem breakers, conductor sizes and available fault current.
- This is not the professional advice of a licensed electrician. Check the result against the electrical code your jurisdiction enforces before you install anything.
Sizing the service or feeder needs demand factors, not connected load: use the dwelling load calculator for a one-family house.
Permit-ready PDF report
The same calculation with every NEC reference, your company and the job address, on US Letter. Saved in this browser only.
Door directory
Free for every panel. Prints on US Letter at 7 × 9 in: choose 100 % or Actual size, not Fit to page, and cut on the outer line. Card stock in a sleeve or a full-sheet label lasts longer than plain paper; 408.4(A) asks for a legible and permanent directory on, inside or next to the panel door.
Saved panels Pro
Keep every panel of a job in this browser and print all their directories in one PDF. Nothing is uploaded: back up to a file before you clear the browser or switch devices.
How it works
01
Set up the panel
Name, supply system and number of spaces, the main breaker and the bus rating from the panel label, and the size of the card holder on the door.
02
Walk the breakers
For each space pick Load, Spare breaker or Space, then enter what it feeds and where, the breaker rating, poles and load in VA. A 2- or 3-pole breaker takes the spaces below it.
03
Print and post it
Check the phase totals, print the directory at 100 %, cut it out and put it in the door.
Questions
What does NEC 408.4 require on a panel directory?
What is the difference between a spare and a space?
Why is a phase total higher than my main breaker?
How do I print the directory at the right size?
Which NEC edition does it follow?
Where is my panel saved?
Do I need to sign up?
Common questions
- What size breaker for a dryer?
- What size breaker for a water heater?
- What size breaker for an electric range?
- What size wire for a 60 amp subpanel?
- What size wire for a 100 amp service?
- What size wire for a 100 amp subpanel?
- What size wire for a 150 amp service?
- What size wire for a 200 amp service?
- What size wire for a 400 amp service?
- All wire, breaker and NEC answers
More NEC calculators
- Dwelling load calculatorService size by the NEC optional method
- EV charger load calculationCan my panel handle an EV charger or heat pump?
- Voltage drop calculatorDrop in volts and percent, and a wire size that carries the load
- Conduit fill calculatorFill percent and the smallest conduit size
- Box fill calculatorIs the electrical box big enough?
- Wire size calculatorAmps and distance in, minimum wire gauge out
- Wire ampacity chartNEC 310.16 with your corrections applied
- Wire gauge chartAWG size, mm², diameter and amps
- Ground wire size calculatorEquipment ground by 250.122, service ground by 250.66
- Transformer sizing calculatorkVA, full-load amps and 450.3(B) breaker sizes
- kVA to amps calculatorSingle- and three-phase, both directions
- Pull box calculatorPull and junction box size by 314.28
- Breaker size calculatorWatts or amps to breaker and wire size
Hand the inspector a clean calculation
Every calculator is free, with the full step-by-step result and NEC references on the page. Pro is US$9 a month for PDF reports with your company and the job address.