Transformer sizing calculator

Enter the primary and secondary voltage and the load in kVA or amps, and Busbar picks the smallest standard transformer, gives the primary and secondary full-load current and the largest primary and secondary breaker or fuse that NEC Table 450.3(B) allows. It then sizes the conductors behind those devices from Table 310.16, the primary equipment ground from Table 250.122, and the grounding electrode conductor and bonding jumpers of the separately derived secondary (250.30). It is free with no sign-up; Pro is US$9 a month for a PDF report. It covers transformers of 1000 V and less with conductors at 75 °C terminals and 30 °C ambient, and it is not a licensed electrician's advice.

  • Single and three-phase
  • 450.3(B) breaker sizes
  • No sign-up
Transformer sizing calculator
Transformer
V

Line to line, e.g. 480

V

Line to line, e.g. 208

kVA

For continuous load or room to grow.

75 kVA: 90.2 A primary, 208.2 A secondary

Primary device up to 125 A, secondary device up to 300 A.

NEC 450.3(B) · three-phase, 480 V to 208 V

Size

Load on the secondary
60 kVA
Smallest standard size that carries it
75 kVA

Full-load current

Primary: 75,000 VA ÷ (480 V × 1.732)
90.2 A
Secondary: 75,000 VA ÷ (208 V × 1.732)
208.2 A

Maximum overcurrent protection

Primary only: 125 % of 90.2 A = 112.8 A, next standard size up
125 A
Primary, with secondary protection: 250 % of 90.2 A = 225.5 A, standard size not above
225 A
Secondary: 125 % of 208.2 A = 260.2 A, next standard size up
300 A

Conductors and grounding (copper, 75 °C terminals)

Primary conductors for the 125 A primary device
1 AWG copper
Secondary conductors for the 300 A secondary device
350 kcmil copper
Primary equipment grounding conductor
6 AWG copper
If the primary device is raised to 225 A (with secondary protection): primary conductors
4/0 AWG copper
If the primary device is 225 A: primary equipment grounding conductor
4 AWG copper
Grounding electrode conductor of the secondary system
2 AWG copper or 1/0 AWG aluminum
System and supply-side bonding jumpers
2 AWG copper
  • Table 450.3(B) applies to transformers of 1000 V and less. The NEC does not set the transformer size itself; sizing for the calculated load (Article 220, or 120 in NEC 2026) with room to grow is the usual practice.
  • Conductors are sized so their 75 °C ampacity is at least the rating of the device protecting them, with 90 °C insulation at 30 °C and three current-carrying conductors per raceway; above 600 kcmil they are run in parallel sets of 1/0 AWG or larger. If you protect the primary above 125 % under the primary-and-secondary method, size the primary conductors and their equipment grounding conductor for that larger device, as the rows above show.
  • Secondary conductors must end in a single overcurrent device that protects them, within the length limits of 240.21(C) (for example 10 ft, or 25 ft with conditions). The secondary of a separately derived system needs its own system bonding jumper and grounding electrode conductor (250.30(A)).
  • This is not the professional advice of a licensed electrician. Check the result against the electrical code your jurisdiction enforces before you install anything.

Permit-ready PDF report

The same calculation with every NEC reference, your company and the job address, on US Letter. Saved in this browser only.

Pro, US$9/month

How it works

  1. 01

    Enter the voltages

    Single- or three-phase, and the primary and secondary voltage, line to line for three-phase.

  2. 02

    Enter the load

    In kVA or in amps at the secondary, sized at 125 % if it is continuous or you want room to grow; or pick a transformer size.

  3. 03

    Read the design

    Standard kVA size, full-load amps, maximum primary and secondary protection, conductors and grounding, each with its section.

Questions

What size breaker for a 75 kVA transformer?

At 480 V three-phase it carries 90.2 A; with primary-only protection Table 450.3(B) allows 125 %, rounded up to the next standard size: 125 A. The 208 V secondary carries 208.2 A and takes up to a 300 A main.

Does the NEC say how big the transformer must be?

No. Article 450 sets the protection, not the size. Size it for the calculated load of what it feeds (Article 220, or 120 in NEC 2026), and many designers leave about 20 % spare.

Can I hand the result to an inspector?

The page shows every step with its NEC section, so you can copy it into your permit packet for free. Pro (US$9 a month) downloads the same calculation as a PDF with your company, license number, customer and job address.

Do I need to sign up?

No. Every calculator works without an account. You only need one, with a verified email address, to subscribe to Pro.

Hand the inspector a clean calculation

Every calculator is free, with the full step-by-step result and NEC references on the page. Pro is US$9 a month for PDF reports with your company and the job address.