Can my panel handle an EV charger?
Yes, you can usually check it without a full load calculation: NEC 220.87 (120.87 in 2026) lets you take the highest demand on your utility bill over 12 months, add 25 %, and add the new charger or heat pump. Enter the service rating, that peak demand in kW and the nameplate of what you are adding, and Busbar shows the total, the amps left and whether it fits. It is free with no sign-up; Pro is US$9 a month for a PDF you can attach to the permit. A 30-day recording cannot be used if the home has solar, wind or peak shaving, and the EV charger uses 125% of nameplate in NEC 2020, at least 7,200 VA in NEC 2023, and nameplate in NEC 2026.
- Uses your utility demand data
- NEC 2020, 2023 and 2026
- No sign-up
The 200 A service can carry the added load (81.7 A)
Existing maximum demand at 125% plus the added load is 19,600 VA, within 48,000 VA.
NEC 2023 · 220.87 existing load from measured maximum demand · 240 V
Existing load
- Maximum demand, 12 months of utility data
- 220.87
- 8.00 kW
- Maximum demand at 125%
- 220.87
- 10,000 VA
Added load
- EV charger (EVSE): Larger of 7,200 VA or the nameplate rating
- 220.57
- 9,600 VA
- Total added load
- 9,600 VA
Service
- Existing at 125% plus added load
- 19,600 VA
- ÷ 240 V
- 81.7 A
- Service or feeder rating
- 220.87
- 200 A
- Remaining capacity
- 118.3 A
- 220.87 also requires the feeder to have overcurrent protection per 240.4 and the service overload protection per 230.90.
- Utility demand data is taken as kW at unity power factor.
- This is not the professional advice of a licensed electrician. Check the result against the electrical code your jurisdiction enforces before you install anything.
Permit-ready PDF report
The same calculation with every NEC reference, your company and the job address, on US Letter. Saved in this browser only.
How it works
01
Find your peak demand
Most utilities show the highest 15-minute demand in kW on the bill or the smart-meter portal. Take the highest of the last 12 months.
02
Enter what you are adding
The EV charger nameplate (for example 40 A × 240 V = 9,600 VA), a heat pump or anything else on the new circuit.
03
See the headroom
Busbar adds 125 % of the peak to the new load and compares it with the service rating, in VA and amps.
Questions
What if my utility does not give me demand data?
What if it does not fit?
Which NEC edition does Busbar use?
Can I hand the result to an inspector?
Do I need to sign up?
More NEC calculators
- Dwelling load calculatorService size by the NEC optional method
- Voltage drop calculatorDrop in volts and percent, and a wire size that carries the load
- Conduit fill calculatorFill percent and the smallest conduit size
- Box fill calculatorIs the electrical box big enough?
- Wire size calculatorAmps and distance in, minimum wire gauge out
- Wire ampacity chartNEC 310.16 with your corrections applied
- Wire gauge chartAWG size, mm², diameter and amps
- Ground wire size calculatorEquipment ground by 250.122, service ground by 250.66
- Transformer sizing calculatorkVA, full-load amps and 450.3(B) breaker sizes
- kVA to amps calculatorSingle- and three-phase, both directions
- Pull box calculatorPull and junction box size by 314.28
- Breaker size calculatorWatts or amps to breaker and wire size
- Panel scheduleCircuit directory and phase loads for a panel
Hand the inspector a clean calculation
Every calculator is free, with the full step-by-step result and NEC references on the page. Pro is US$9 a month for PDF reports with your company and the job address.